Poole Bridge will be sandblasted, repaired and repainted teal from 11 January 2027, with the lifting arms enclosed for about 10 months. Here is what is planned.
Work to repair and repaint Poole Bridge will start on 11 January 2027 and is expected to last about 10 months, BCP Council said on 6 November. For the whole of that time the bridge’s lifting arms will sit inside a large protective enclosure.
The bridge has carried people across Poole Harbour since 1927 and is coming up to its centenary. The council says the job is to fix areas of corrosion and give the steel a new protective coat so that it lasts for decades and needs fewer unplanned repairs.
What the work involves
The main task is stripping off a rubber-based paint coating that was put on the bridge around 25 years ago. The council says that coating cannot simply be painted over. Instead:
- the old paint will be removed by specialist sandblasting
- corroded steelwork will then be repaired
- a new protective coating will go on, in the bridge’s familiar teal
The enclosure over the lifting arms is there, the council says, “to protect the harbour waters and surrounding environment, and to provide a controlled environment for painting”. The contractor is Octavius Infrastructure.
Who is paying, and why now
The repairs are part of a £6 million investment in the long-term reliability of Poole Bridge and the Twin Sails bridge, along with the variable message (VMS) signs that go with them. The money comes from the Community Infrastructure Levy, the charge paid by developers, and councillors approved the funding in July 2025.
At their busiest, the council says, the two bridges carry upwards of 20,000 journeys a day between them.
Cllr Andy Hadley, BCP Council’s portfolio holder for highways maintenance, said: “Poole Bridge has served our communities for almost 100 years and remains one of the most important transport links across the harbour.
“These improvements are about protecting that link for future generations by making 20th century infrastructure fit for 21st century commuters.
“By tackling corrosion and providing a new painted seal now we can significantly improve the durability of the bridge and maintain its structural integrity.
“I know this work will be highly visible but carrying out planned maintenance now is the best way to make sure Poole Bridge continues to serve residents, businesses and visitors for many years to come.”
What it means for you
- Dates: work starts on Monday 11 January 2027 and should run for about 10 months, which takes it to around November 2027.
- Closures: the release does not say whether the bridge will close to traffic or people on foot, or how bridge lifts for boats will be handled. The council says a more detailed timeframe will be published before work starts, and we will add it here when it is.
- The look of it: expect a large enclosure over the lifting arms for most of 2027, then the bridge back in teal.
- Twin Sails: it shares the same £6 million pot, but the release sets out no dates for work on it.
For other closures across Bournemouth, Christchurch and Poole, see our roadworks and travel page.